In a tightly scheduled, large-scale project, the 15/33 runway at Salzburg Airport was refurbished. The concrete runway from the 1960s would remain as the foundation for the new covering layer consisting of 120,000 tons of asphalt.

David Hawel

26.07.2019

In a tightly scheduled, large-scale project, the 15/33 runway at Salzburg Airport was refurbished from 24 April to 28 May 2019. The concrete runway from the 1960s would remain as the foundation for the new covering layer consisting of 120,000 tons of asphalt.

 

 

Part of this giant project was the core drilling of more than 800 holes for the runway illumination as well as an impressive 10.8 km of floor cuts. In fact, three special construction companies worked simultaneously in order to finish the works on time: Possehl Spezialbau, ÖBA and OAT. With regards to diamond tools and on-site support, they referred to TYROLIT as their professional partner.

 

 

10.8 km of floor cuts and more than 800 core drills with no time to lose

 

Key of the renovation of „Salzburg’s longest straight road” (2,850 meters) was to maintain the current concrete runway as a base layer, and, thus, to avoid an extra 4,000 truck rides for its removal. With a beheading machine, the 45 m wide runway had to be divided into smaller concrete panels, which should act as a tension-free base layer. This required over 10.8 km of preparative floor cuts with a width of 15 mm and a depth of 300 mm, amounting to 240 cuts of 45 m each. With a time span of only 5 days, this was pretty challenging, yet feasible. The TYROLIT floor saw blades in TGD® Technology were just perfect for the task and smoothly managed the sometimes ingenious solutions the cutting professionals and TYROLIT application engineers came up with.

After the new layer of asphalt was finished, over 800 core drills for the state-of-the-art LED-illumination of the runway had to be done – again within only 5 days. For this challenge, the professional drillers used TYROLIT drill bits with TGD® Technology, which proofed to be just right for the material mix of concrete and asphalt. The drilling as well as the subsequent tasks were finished within the planned period, and so the airport was also reopened as scheduled.

TYROLIT diamond tools used for the project:

Floor saw blades with TGD® Technology

 

 

For the floor sawing tasks at Salzburg Airport there were used three different specifications of TYROLIT floor saw blades with TGD® Technology: FSL***-C, FSM***-C und FSH***-C. All are perfectly suited for cured concrete with soft to very hard material aggregates and are laser-welded up until diameters of 1,200 mm. The intelligent distribution of the grain enabled by TGD® Technology ensures constantly high cutting speeds and smooth running.

FSL***-C in TGD® Technology

 

for machines up to 15 kW

FSM***-C in TGD® Technology

 

for machines up to 25 kW

FSH***-C in TGD® Technology

 

for machines up to 50 kW

CDL*** core drill bits in TGD® Technology

 

TYROLIT CDL*** core drill bits with TGD® Technology ensure constantly high cutting speeds as well as smooth operation and come with a very long life span. They are equally suited for the drilling of concrete and asphalt and were, thus, the perfect choice for the drilling of the holes of the LED-illumination at Salzburg Airport.